Percentage of Completion Revenue Recognition in Odoo for Contractors
Set up percentage of completion revenue recognition in Odoo 19 and 20: cost-to-cost method, contract asset and liability journals, WIP schedule reports.
Contractors who bill on certificates or milestones rarely earn revenue at the same pace they invoice it. Our Odoo ERP for construction setup closes that gap so the profit and loss shows earned revenue, not just billed revenue.
Related service: Odoo implementation services — fixed-scope implementations with a named senior team.
This guide is for CFOs, controllers and finance leads at contractors, EPC firms and project-based engineering companies running Odoo 19 or 20. If you are new to the ledger side of Odoo, start with how Odoo Accounting works.
What is percentage of completion revenue recognition?
Percentage of completion revenue recognition spreads contract revenue and profit over the life of a project in line with measured progress. It replaces the completed contract approach, which books everything at the end.
Under IFRS 15 and ASC 606, revenue on work satisfied over time follows measured progress. IFRS 15 paragraph 35 says when that applies, including work that creates an asset with no alternative use plus an enforceable right to payment for work done to date.
Most construction contracts meet that test, which is why the percentage of completion method is the norm for contractors. It is general guidance only: confirm the treatment for each contract type with your auditor under IFRS 15 or ASC 606 before you configure anything.
Which progress methods can you use: cost-to-cost, milestones or surveys?
You can measure progress with an input method such as cost-to-cost, or an output method such as surveys, milestones or units delivered. IFRS 15 paragraphs B15 to B19 describe both families.
| Method | How progress is measured | Typical use | Where the data sits in Odoo |
|---|---|---|---|
| Cost-to-cost (input) | Costs to date / estimated total cost | General contracting, EPC | Analytic account of the project, analytic budget |
| Labor hours (input) | Hours to date / total estimated hours | Labor-heavy fit-out, services | Timesheets on project tasks |
| Survey of work done (output) | Engineer or QS approved percentage | Certified progress claims | Sales order line delivered quantity |
| Milestones (output) | Milestones reached / total | Phased contracts | Project milestones linked to the sales order |
| Units delivered (output) | Units installed / total units | Repetitive units, modular builds | Delivered quantity on the sales order |
The cost-to-cost method is the most common in construction WIP accounting. IFRS 15 B19 warns that costs which do not show progress, such as wasted materials or inefficiencies, should be left out of the calculation.
How does the cost-to-cost method work with a worked example?
Divide costs incurred to date by total estimated costs, apply that percentage to the contract price, and subtract what you already recognized. The difference is this period's revenue.
The numbers below are illustrative, for one contract at the end of month six:
- Contract price: $1,000,000, including approved variations.
- Estimated total cost: $800,000, updated by the project manager this month.
- Cost incurred to date: $320,000, from the project's analytic account.
- Percent complete: $320,000 / $800,000 = 40%.
- Earned revenue to date: 40% x $1,000,000 = $400,000.
- Billed to date: $450,000 of progress invoices posted in Odoo.
- Result: billed exceeds earned by $50,000, so the contract is over billed by $50,000.
If billing had been $350,000, the contract would be under billed by $50,000. When the estimated cost exceeds the contract price, recognize the expected loss at once, not over time.
What is the difference between a contract asset vs contract liability?
Under billing is a contract asset because you earned more than you invoiced; over billing is a contract liability because you invoiced more than you earned. These two balances are the heart of a WIP schedule.
| Position | Older US label | IFRS 15 / ASC 606 label | Balance sheet side |
|---|---|---|---|
| Earned more than billed | Costs and estimated earnings in excess of billings | Contract asset | Current asset |
| Billed more than earned | Billings in excess of costs and estimated earnings | Contract liability | Current liability |
| Invoiced and due | Accounts receivable | Receivable | Current asset |
| Advance received before work | Customer advance | Contract liability | Current liability |
IFRS 15 paragraph 107 calls a contract asset a right to consideration for work transferred, and paragraph 106 defines a contract liability as an obligation to transfer work already paid for or due. Keep both separate from receivables.
How do you set up Odoo WIP accounting for contracts?
Set up accounts, analytics and a revenue product first, so every invoice and cost lands on the right contract. The setup below works in Odoo 19 and Odoo 20.
- Chart of accounts: add Contract Asset (current asset), Contract Liability (current liability), Contract Revenue (income) and, if needed, Provision for Contract Losses.
- Analytic plan: create a Projects plan so each contract has its own analytic account, as covered in our guide to Odoo analytic accounting plans and budgets.
- Revenue product: a service product that posts to Contract Revenue, linked to the project.
- Cost capture: vendor bills, purchase orders, expenses and stock moves carry the project's analytic distribution.
- Budget: an analytic budget in Odoo holds the estimated total cost per contract.
- General journal: a "WIP Adjustments" miscellaneous journal keeps period-end entries easy to find.
The BOQ, progress certificates and variation orders sit upstream of this. Our post on Odoo for construction: BOQ, progress billing and cost control covers that side.
What journal entries does Odoo construction accounting need each period?
Post invoices to Contract Revenue as usual, then post one WIP adjustment per contract at month end that reverses on the first day of the next month. This keeps billing simple and the profit and loss correct.
| Situation | Debit | Credit | Reversal |
|---|---|---|---|
| Progress invoice posted | Accounts Receivable | Contract Revenue (and tax) | None |
| Under billed at month end | Contract Asset | Contract Revenue | First day of next month |
| Over billed at month end | Contract Revenue | Contract Liability | First day of next month |
| Expected loss on a contract | Contract Loss Expense | Provision for Contract Losses | Update each period |
| Advance received before work | Bank | Contract Liability or Customer Advance | Released as work is billed |
With the example above, the month six entry is a $50,000 debit to Contract Revenue and credit to Contract Liability. Revenue for the contract to date then shows $400,000, matching earned revenue.
Using reversing entries means each month starts clean and you recalculate from cumulative totals. That avoids drift from small estimate changes and is easier to audit than running balances.
How do you post over under billing entries in Odoo 19 and 20?
You can post them as manual journal entries with a reversal date, or from the Accrued Revenue Entry action on sales orders. Both create an entry and its reversal in one step.
The accrued orders wizard behind this action lets you enter an accrual date, a reversal date (by default the next day), a journal, an account and a manual amount. The manual amount suits cost-to-cost results calculated outside the order.
In Odoo 20 the wizard adds an accrual type. "Invoices to be issued" books delivered but not invoiced amounts, and "Invoiced not delivered" books the reverse. If you keep each sales order line's delivered quantity equal to measured progress, Odoo calculates the gap for you.
For output methods, milestone invoicing in Odoo updates the delivered percentage when a milestone is reached. A user on the Odoo forum also explains a percent complete unit of measure on order lines so each invoice bills only the change since the last one.
What is native in Odoo and what needs a module?

Odoo covers cost capture, budgets, accruals and reports natively; the cost-to-cost calculation per contract is the piece you configure or automate. An Odoo forum user asking about percentage of completion under IFRS 15 was told there is no built-in automatic revenue recognition.
| Need | Native in Odoo 19/20 | Configuration | Module or custom build |
|---|---|---|---|
| Costs per contract | Analytic accounts, project profitability | Analytic distribution on bills and stock | None |
| Estimated total cost | Analytic budgets | One budget line per contract | None |
| Time-based deferral | Deferred revenue on invoice lines | Deferred revenue account | None |
| Under and over billing entry | Accrued Revenue Entry, manual entries | WIP journal and accounts | Optional batch automation |
| Cost-to-cost calculation | No | Spreadsheet or pivot | Scheduled action or custom module |
| WIP schedule report | Pivots, spreadsheets | Saved views | Custom accounting report |
| Loss provision | Manual entry | Provision account | Optional alert |
Deferred revenue in Odoo spreads amounts by days or months between a start and end date. That fits maintenance contracts, not cost-based progress, so do not use it for percentage of completion.
Before buying any third-party app, list the outputs your auditor wants. A small scheduled action on top of standard Odoo often does the job and survives upgrades better than a heavy module.
Which reports form a WIP schedule in construction?
A WIP schedule in construction combines contract value, estimated cost, cost to date, percent complete, earned revenue, billed to date and the over or under billing for each contract. Odoo holds every input; you assemble the view.
- Project profitability: the project profitability dashboard shows costs and revenues linked to the project's analytic account, split into expected, to invoice and invoiced.
- Analytic budget report: compares budgeted cost with achieved and committed cost, including confirmed purchase orders not yet billed.
- Analytic items pivot: costs to date per contract, by account group.
- Partner ledger and aged receivable: billed to date and retention still due.
- Balance sheet: Contract Asset and Contract Liability balances after the WIP entry.
Timesheets are a common trap. Their cost appears on the project's analytic account, but the general ledger gets labor cost through payroll, so check both before using hours in the cost-to-cost calculation.
How does period-end close work for percentage of completion?
Run the WIP routine in the same order every month, then lock the period. Most of the risk is in the cost estimate, not the entry.
- Post all vendor bills, expenses and stock moves for the month with the right analytic account.
- Accrue costs for work done but not yet billed by subcontractors.
- Ask each project manager to update the estimated total cost and record why it moved.
- Export the WIP schedule and calculate percent complete and earned revenue.
- Post under and over billing entries with a reversal on the first of next month.
- Book or update loss provisions for contracts expected to lose money.
- Review the balance sheet lines, then set a lock date in Odoo.
The Odoo year-end and lock date guide explains how a lock date blocks changes to posted entries on or before it. Our Odoo month end close checklist fits the WIP routine into the wider close.
Which industries need ifrs 15 Odoo construction setups?
Any business with long contracts that span reporting periods needs percentage of completion, not only general contractors. The cost driver and the progress measure differ by industry.
| Industry | Pain or cost driver | Odoo approach | How iVentureTeam helps |
|---|---|---|---|
| General contracting | Subcontractor costs arrive late | Analytic accounts per contract, cost accruals | Design the monthly WIP routine |
| MEP subcontractors | Materials bought ahead of install | Exclude uninstalled materials from cost-to-cost | Set stock and analytic rules |
| EPC and infrastructure | Long contracts, many variations | Budgets revised per variation | Build the WIP schedule report |
| Interior fit-out | Labor-heavy, short phases | Labor hours or milestones | Configure milestone invoicing |
| Engineered equipment | Custom builds over several months | Cost-to-cost with manufacturing costs | Link production costs to the project |
For the stock side of long builds, such as goods sitting in production, see our guide on Odoo work in progress inventory. This post stays on revenue and contract balances.
How iVentureTeam helps with percentage of completion revenue recognition in Odoo

We turn your auditor-approved revenue policy into Odoo accounts, analytics and a monthly routine your team can run. We have delivered 150+ ERP projects across 35+ countries with 40+ Odoo specialists, led by a consultant with 13+ years in Odoo.
- Policy to setup: map your progress method, accounts and journals to Odoo 19 or 20.
- Cost capture: analytic rules on purchases, stock, expenses and timesheets so costs to date are complete.
- Automation: a scheduled action or small module that calculates cost-to-cost and posts reversing WIP entries, built through our Odoo customization services.
- Reporting: a WIP schedule your auditor can tie to the general ledger.
- Rollout: delivered as part of Odoo implementation services, with a parallel month before go-live.
To size the work, try the Odoo implementation cost calculator.
Odoo cost tracking case study: Fernando Tax Management
Revenue recognition is only as good as the cost data per engagement, and this project was about capturing those costs where the work happens. Fernando Tax Management B.V. is a Dutch tax practice, not a contractor, but the cost tracking problem is the same.
The firm's legacy system relied on hand-keyed data, produced duplicate records and made journal entries and cost tracking convoluted. A hidden journal lines issue was also obscuring accounting data.
We migrated the firm to Odoo 18, built a custom office cost tracking workflow into Sales and Purchase, resolved the hidden journal lines issue and developed localized compliance reports. The project took 10 weeks.
The firm reports a 60% reduction in manual data entry. Read the Fernando Tax Odoo accounting automation case study.
The bottom line on percentage of completion revenue recognition in Odoo
Odoo 19 and 20 can run percentage of completion accounting well once you add contract accounts, analytic budgets and a disciplined monthly WIP entry. Only the calculation itself needs a spreadsheet, a scheduled action or a small module.
Agree the method and the costs that count with your auditor first. Then capture costs by contract, update estimates monthly, post reversing entries and lock the period. The result is a profit and loss that shows what each contract really earned.
Ready to set up WIP and revenue recognition in Odoo?

Get your contract accounts, WIP schedule and month-end entries designed by people who know Odoo Accounting. Plan your Odoo WIP accounting setup with us, call +91-90235-15208, or email business@iventureteam.com.
Frequently Asked Questions
Does Odoo support percentage of completion revenue recognition?
+
Not as a one-click feature. Odoo provides project costs, analytic budgets, accrual entries and reports, and you calculate percent complete in a spreadsheet, a scheduled action or a small custom module.
What is the cost-to-cost method?
+
It measures progress as costs incurred to date divided by total estimated costs. That percentage times the contract price gives earned revenue to date, and the change since last period is this period's revenue.
What is over billing and under billing?
+
Over billing means you invoiced more than you earned, shown as a contract liability. Under billing means you earned more than you invoiced, shown as a contract asset.
Can I use Odoo deferred revenue for construction contracts?
+
Usually not. Odoo's deferred revenue spreads amounts evenly by days or months between two dates, while construction revenue follows cost or work progress. It suits maintenance and service contracts instead.
What journal entry records under billing in Odoo?
+
Debit Contract Asset and credit Contract Revenue for the gap between earned and billed revenue, dated at month end. Set a reversal date on the first day of the next month and recalculate each period.
How do I get costs per project in Odoo?
+
Give each contract an analytic account and add it to vendor bills, purchase orders, expenses and stock moves. The project profitability dashboard and analytic reports then show costs to date per contract.
What changed in Odoo 20 for accruals?
+
The Accrued Revenue Entry wizard in Odoo 20 has an accrual type that separates invoices to be issued from invoiced but not delivered amounts. That maps well to under billing and over billing.
Is percentage of completion required under IFRS 15 and ASC 606?
+
Both standards require revenue over time when a contract meets the over-time criteria, measured by an input or output method. Confirm the right method for your contracts with your auditor.
How should I handle a loss-making contract?
+
Recognize the full expected loss as soon as it becomes likely, not spread over the remaining work. Post it to a provision account in Odoo and update it every period as estimates change.
Free industry walkthrough
Using Odoo for your industry?
We walk you through how Odoo handles a business like yours and what to set up first, based on projects we've delivered.
Free, with no obligation. A senior consultant replies within 12 business hours.
Free Odoo tools
All tools- Odoo Health CheckVersion, modules, findings and upgrade cost
- Odoo App SelectorWhich apps you need, by industry
- Odoo Project EstimateIndicative cost and timeline in minutes
- Odoo Implementation Cost CalculatorImplementation cost and timeline, in minutes
- Odoo Migration Cost CalculatorVersion jump or legacy ERP, priced in minutes
Continue reading
Spreadsheets After ERP Implementation: Why Odoo Users Keep Excel
Why teams keep Excel after an Odoo go-live, the hidden risks of shadow spreadsheets, and a fix plan using Odoo 20 Spreadsheet, Dashboards and imports.
Odoo ERP Implementation in Saudi Arabia: ZATCA, Arabic, Cost, Timeline
Odoo ERP implementation in Saudi Arabia: Odoo 19 vs 20, ZATCA Phase 2 onboarding, Arabic invoices, GOSI and WPS payroll, hosting, cost and timelines.
Odoo Post Implementation Review: 30/60/90 Day Checklist and Template
Run an Odoo post implementation review at 30, 60 and 90 days: go-live checklist, six KPIs, Odoo 19 and 20 checks and a report template you can copy.